Works to public right of way network

Thursday 5 December

 

Works to public right of way network between Lindrick Road and Southwell Lane to Penny Emma Way, Kirkby in Ashfield.

The initial tree works phase is nearing completion. Trees and shrubs have been pruned back away from the footpaths and grass and scrub has been flailed back.

The next phase to improve the surfacing on the footpaths is due to commence on Monday 9th December. Works will continue for two weeks until the 20th December and resume on 6th January 2020.

We ask you to take care whilst walking along the paths and please be mindful of signage that will indicate which paths are being worked on.

The works are due to be completed by the end of January (weather depending).